Shimla, 09 September 2024: Shri Sushil Sharma, CMD SJVN Limited visited 1320 MW Buxar Thermal Power Project at Chausa, Bihar. Accompanied by CEO, STPL & senior officials, Shri Sushil Sharma took stock of key areas viz Main Boiler, Turbine Area, CCR at 17m level, FOPH & CHP area to assess project progress.
He had Progress Review Meeting with Head of Departments of project and senior officials from M/s L&T. He emphasized the importance of working tirelessly to meet the target of commissioning Unit-1 by 31st December 2024.
He asserted entire STPL Team to put forth their best efforts in achieving critical milestones of Boiler Light-Up of Unit -1 by 30th Sept. 2024 & commissioning by 31st Dec. 2024. Additionally, He congratulated entire Team on recent recognition of SJVN as a Navratna CPSE.